Answer: It depends on status of the task: “Not completed” or “Completed”.
- The previous task is “Not completed”: The next task will not appear until you complete the previous task. This behavior is intended to prevent tasks from increasing too much over time.
- The previous task is “Completed”: The next task will appear in the following way.
- Daily repeat: It will appear at 00:00 the day after the previous task deadline.
- Weekly repeat: It will appear at 00:00 on Monday of the week after the previous task deadline.
- Weekly repeat (If you specify multiple days of week): It will appear at 00:00 the day after the previous task deadline.
- Monthly repeat: It will appear at 00:00 1st the month after the previous task deadline.
- Yearly repeat: It will appear at 00:00 1st Jan the year after the previous task deadline.